       Environment Agency, Flood Risk Management

Ian Tripp, Solent & South Downs, Asset System Management Technical Specialist

  Introduction

   3. Works that the Environment Agency do in Romsey

  1. Flood Warnings
  2. Regulate works near to the main river
  3. Advise Planning Authority on flood risks
  4. Review flood risk assessments
  5. Maintenance and Inspection of assets
  6. Undertake long term Strategic Studies
    • Catchment flood managment plans
    • Strategy studies for specific risk areas
  7. Leads on to future works

  Maintenance

  • Routine Maintenance - £25,000 annually
  • Weed cutting, channel clearance
  • Minor repairs - structures
  • Water level control
  • Clearance of grilles etc
  • Closure of flood gates
  • Operation of flood control structures

  Photo: Test at Timsbury
  Weedboom

  Asset Surveys and Inspections

  • All Flood Defence structures recorded on Database
  • Regular Inspection between 6 months and 3 years
  • High risk areas more frequently, low risk less often


Condition of flood Defences

  Recent Maintenance Works

  • Repairs to Fishlake Stream embankment by World of Water, sheet piling into embankment to stabilise
  • Raising footpath and Fishlake Stream enbankment downstream of Fishlake Meadows road bridge
  • Improvements to the Timsbury Weedboom site to make handling weed more efficient

 

   4. Future Plans

  Future Maintenance Works

  • Improvements to the Fishlake/Oxlease Siphon
  • In design this year
  • Construct next year
  • Safer two stage trash grille
  • Penstock to give more water control

  More Future Maintenance Works

  1. Fishlake to Oxlease Penstock (Industrial Estate) to be repaired in the next 2 years
  2. Review Management of Fishlake Stream where narrowing has taken place opportunity for habitat enhancements
  3. System Asset Managment Plans - 50 year needs of a river system such as Romsey
    • Considers costs and benefits
    • AAD £500k, Pilot study C/B 1:3+
    • Direct funding to hight risk systems such as Romsey

Penstock/sluice from Fishlake
Meadows to Oxlease Stream


Maintenance

  Future Major Works

  • Dependant on CFMP and Strategies
  • CFMP Policy is likely to be P5:
  • 'Take further action to reduce flood risk now and in the future'
  • 1280 properties at risk now
  • 1370 in future with climate change
  • Annual average damages £1.5m rising to £2m
  • 1 in 25 year event damages estimated £11.5m
  • 1 in 100 year event damages estimated £24.3m
  • Future 1 in 100 year damages estimated £28m
  • Seen as high priority for detailed strategy

  CFMP Romsey

  • Key driver for future is climate change
  • Impact of new development
  • Requirement to use Sustainable Urban Drainage Systems (SUDS) to manage surface run off
  • Standard of protection is low in some parts of the town 1 in 5 year)
  • Improvements to channel conveyance (Tadburn Lake) and localised raising of banks
  • Managment of flows
  • Creation of Washlands and strategic storage with opportunities for habitat enhancements

Home| Join/contact| Diary | Committee | Documents | News Sheet | Buildings Preservation Trust
Town Reports | Look at Romsey | Flood Forum | Romseynet